The Roads - civil construction is in the final months of completion.

Main roadworks, kerbs and guttering are complete, producing an extension of Trezise Lane and new road - St Martins Place. Asphalt will be applied in the last stages of the project.

Sewerage reticulation and stormwater drainage are complete and currently being tested.  

Trenches have been prepared for electrical and NBN cables to be laid in the next fortnight. Once complete, footpaths will be prepared for cement pouring.

Following this, the project team will progress through the final testing and certification process, with site completion on track for early May.

Settlement timeframes

Land titles are anticipated to be available late May – early June.

This timeframe remains indicative only, based on the current status of civil works. Settlement is also dependent on receiving a Statement of Compliance from the City of Ballarat once all civil works and testing are complete.